Golf & Grounds Departments

Golf & Grounds Departments
Pete Dye's #10 Golf Hole @ TFP

Friday, May 6, 2011

Drainage Project on 10 and 16 Completed


The drainage project on #10 and #16 is complete and performing well. The new drainage systems will aid in reducing plant and soil saturation by reducing excess water and prolonged leaf wetness in the areas it was installed.

First Step: Removing Sod

Second Step: Trenching Drainage Lines

Third Step: Drainage Trenches Ready for Sand

Forth Step: After Installing Drain Lines Sand is Added

Fifth Step: Prepping Drain Lines for Sod

Drainage Project Completed

No comments: